Washington ContractorCheck

Bids, contracts and permits for Washington remodels and ADUs

How to get comparable bids, what to put in a written contract, when a permit is needed and where accessory dwelling units fit.

Large residential projects go wrong more often from unclear scope and permits than from bad workmanship. L&I’s advice to homeowners is plain: get at least three written bids, compare them carefully, check references, get a written contract you understand and consider a performance bond on larger projects. Here is how to apply that.

Get comparable bids

Give each contractor the same written scope: dimensions, materials by brand or grade, fixtures, finishes, demolition, disposal and who is responsible for design drawings. Ask them to list allowances (amounts set aside for items you have not yet chosen) separately, and to list exclusions. A bid that is much lower than the others usually leaves something out.

Check the paperwork on every bidder

Verify the registration, bond and insurance for each bidder on the L&I tool. Note the disclosure statement: for residential projects of four or fewer units with a contract of $1,000 or more, the contractor must give you one before starting work (RCW 18.27.114).

What belongs in the contract

Who draws the plans

Larger remodels and most ADUs need drawings for the permit. Washington does not require an architect for that work on smaller homes: RCW 18.08.410 lets anyone do design work and prepare construction documents for a residential building of up to four dwelling units, or for a garage, shed or similar structure that goes with it. Many plans are therefore drawn by a building designer or by the contractor. Before you sign, ask who prepares the drawings, whether any part, such as a beam or foundation, will need an engineer, and who answers and pays for corrections the city asks for during plan review.

Permits

Most structural, electrical, plumbing and mechanical work needs a permit from your city or county building department, and electrical permits often come from L&I. Cities also review zoning setbacks, critical areas such as steep slopes and shorelines, and trees. The permit belongs to the project; ask that it be pulled in the licensed contractor's name so that inspections and responsibility are clear, and keep the final inspection sign-off with your house records.

Under RCW 18.27.110 a city, town or county must verify that a contractor is registered before issuing a building permit for its work, print the registration number on the permit, and give the applicant written notice about the risks of using an unregistered contractor. If a contractor asks you to pull the permit yourself as an owner, ask why: the permit is where the registration check happens.

Accessory dwelling units

Washington has encouraged accessory dwelling units (ADUs, including backyard cottages and basement or garage conversions) in recent years, and cities such as Seattle and Bellevue publish their own ADU rules, fees and permit steps. If you are building one, use a builder with ADU experience, ask to see a finished project and get the city's pre-application guidance before signing. Our sister site ADU Builder Index lists Seattle and Bellevue ADU builders with the same positive-only verification approach.

State law sets a floor for local ADU rules. Under RCW 36.70A.681, cities and counties planning under the Growth Management Act must, within urban growth areas:

There are also limits on off-street parking requirements, especially within half a mile walking distance of a major transit stop. The rules do not apply on lots with critical areas or their buffers, and RCW 36.70A.680 still lets local governments restrict short-term rentals of ADUs and prohibit ADUs on lots not served by public sewer. Each jurisdiction had to adopt the rules with its next periodic comprehensive plan update; where it has not, the state rules override conflicting local ones. Ask your city's planning desk which version applies to your lot before paying for design work.

During the job

  1. Pay only for completed work, and collect lien releases.
  2. Approve every change in writing before it is done.
  3. Photograph work before walls close up.
  4. Do not let the final payment go until inspections have passed and punch-list items are done.

If you have a dispute

Try to resolve it in writing with the contractor first. Then contact L&I about the registration, and consider whether the bond deadlines in RCW 18.27.040 apply to you: a residential homeowner suing on the bond for breach of contract must file within two years of substantial completion or abandonment of the work. If a judgment against a registered contractor goes unpaid after the bond, RCW 18.27.410 sets up a homeowner recovery program for primary residences; see our guide to bonds and insurance for the conditions. For an unregistered contractor, remember that they may be barred from suing for payment under RCW 18.27.080, and that L&I takes reports about unregistered work.

Updated 2026-10-03.

General information only, current as of the date above. The information on Washington Contractor Check is not a recommendation or a guarantee of anyone's work. A license record shows registration status on the date shown, not workmanship, insurance coverage at the time of your job, or suitability for your project. Confirm license, insurance and permits directly before you hire. Rules and programs change; check the official sources linked in this guide.

Find contractors